Table No.6.1.1 Development plan time frame by weeks
Steps
Time frame for completion in Weeks
Tasks
Milestone
1
Week 01-06
1. Title due diligence
2. Management Requirements & Project Development Guidelines(PDG)
3. LDC Appointment
4. Master plan, block planning, phasing of development 5. Appointment of Surveyorand Site Survey
6. Appointment of Soil Test Vendor and SBC Test
7. Traffic analysis (Preliminary) 8. Checklist, Lesson Learnt
9. Airport Authority of India (AAI) approval
2
Week 07
1. Business Funding plan
3
Week 08-11
1. Joint Development Agreement (JDA)
2. Core detailing and concept plan completion
3.Basic MEP Coordinated
"Week-11 Project Concept Complete, Business plan internal sign off"
4
Week 12-19
1. Appointment of excavation contractor and blasting permission"
2. Site barricading based on Govt. approved survey
3. Environmental clearance (EC) & Consent for Establishment (CFE) Approval
4. Final FireĀ Approval (Provisional)
5. Municipal approval
5
Week20-27
1. Start of Excavation - Phase 1 (Excavation which do not require Environment Clearance)
2. Design development
3. Supplementary Development Agreement (SDA)
4. Detailed MEP coordinated
5. Site Logistics, Delivery strategy and Procurement strategy
"6. Environmental clearance(EC) & Consent for Establishment (CFE) Approval (Continued)"
"Week-27 (Check Point) Design Development Review & Sign-Off by All Stakeholders"
6
Week 28-32
1. Excavation Brief Sign-off
2. Tender package
3. Debt Syndication and Conditions Precedent (CP) Compliance
"4. Environmental clearance(EC) & Consent for Establishment (CFE) Approval (Obtained)"
5.Completion of Excavation - Phase 1
7
Week 32-36
1. Start Site excavation - Phase 2, Post Environmental Clearance (EC)
2. Budget based on design
3. BOQ Qty Validation
4. Align Budget as per validated BOQ and Budget Approval
5.Business/Funding plan Alligned to Approved Budget
6. Handover to PMO-Stage 1 (Tender drawings and budget)
7. Issue of GFC (Coordinated Structural &MEP)
8. Identification of GC
9. Debt Syndication and CP Compliance (Continued)
"Week-33 Excavation handover to PMO"





"Week-36 Handover to PMO - Stage 1 "
8
Week 37-38
1. Handover to PMO Stage-2 (with GFC)
"Week-38 Handover to PMO - Stage 2 "
9
Week 39-46
1. Validation of Procurement Strategy
2. Completion of GC identification
3. Structural steel NSC Identification
"Week-47 Issue of LOA to GC"
10
Week 47-53
1. NSC identification (MEP & Other packages)
2. Structural steel NSC Identification
3. Debt Syndication and CP Compliance - Completion
"Week-53 Issue of LOA to Structural Steel"
"Week-53 Fund Disbursement and Start on site"
11
Week 54-62
1. GC and NSC contract award
2. Site Mobilisation
3. Shop drawings approval of Structural Steel
4. NSC identification (MEP & Other packages)